Development Contract Claims Are Not Subject to 90-Day Limit
Focus Column - Land Use - By Daniel J. Curtin Jr. - In a case of first impression, an appellate court has held that a claim for breach of a development agreement is subject to the statute of limitations applicable to breach-of-contract claims, except to the extent that the claim challenges a decision made under the Subdivision Map Act. Legacy Group v. City of Wasco , 106 Cal.App.4th 1305 (Cal. App. 5th Dist. 2003).




Land Use
By Daniel J. Curtin Jr.
In a case of first impression, an appellate court has held that a claim for...